Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Lag days not included in project duration
Comments
-
I guess the task with lag days is not on the critical path - so it does not affect the length of the project.
atus
-
Deborah,
(Well, I had a long answer to the wrong question - so I deleted it)
In the example you showed, the 2d delay may or may not be part of the total duration.
For a particular task, the duration is elapsed effort. (That was the long email)
For summary tasks, it tasks the start and end dates to determine duration.
Summary Task
Task 1 - 3 days
Task 2 - 3 days with a 2 day lag
Total duration is 8 days.
What you have is
Task 1 - 7.5 days
Task 2 to 4 - all occuring within that 7.5 days
so no impact to the final duration
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives