Lag days not included in project duration
Comments
-
I guess the task with lag days is not on the critical path - so it does not affect the length of the project.
atus
-
Deborah,
(Well, I had a long answer to the wrong question - so I deleted it)
In the example you showed, the 2d delay may or may not be part of the total duration.
For a particular task, the duration is elapsed effort. (That was the long email)
For summary tasks, it tasks the start and end dates to determine duration.
Summary Task
Task 1 - 3 days
Task 2 - 3 days with a 2 day lag
Total duration is 8 days.
What you have is
Task 1 - 7.5 days
Task 2 to 4 - all occuring within that 7.5 days
so no impact to the final duration
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 412 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives