Report builder Creating Dependencies between multiple sheets
Comments
-
can you provide more details about what you are trying to do?
-
Hi...I have the same question...
I typically manage or consult on multiple interdependent projects. I've tried managing dependencies across projects in different ways but none of them have been super successful.
For example, Project A - call it Telephone installation - has a dependency on Project B - call it, Network Infrastructure upgrade. They are being managed as two separate workstreams because of their content and resources, but at some point, work on project A will stop if Project B hasn't reached a certain point (usually a milestone).
I would like to (in the best case) show the dependency actually in the dependent project so that Project B is late, the remaining tasks of Project A slip. Alternate would be okay if I could just report on the dependencies and highlight pending problems.
Any suggestions would be appreciated...
Rob
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives