Adding start and end date columns/fields
KimCraig
✭✭
If I did not start with a template that includes start, end date and duration, is there a way to add those so that end date automatically calculates from the start date plus duration?
Comments
-
You'll need to add a start and finish column that are set as dates, then right click on the header of a column and choose edit project settings to enable dependencies and duration.
-
Or you could add the appropriate columns as listed above and enter
=[Start Date]@row + Duration@row
This will automate the End Date without having dependencies enabled.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65K Get Help
- 443 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 149 Just for fun
- 70 Community Job Board
- 497 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives