Sign in to join the conversation:
I am trying to automate the ryg ball if i go:
15 days past start date and my complete is blank, red ball
10 days past start date and complete is blank, yellow ball
otherwise green ball.
Any help is appreciated
You can use the symbols as a dropdown and then the IF statement where the result will be "Red", "Green" or "Yellow". That text as the output of the function will form the colors.
Another thing to think of is that only updates when the sheet is opened and saved again. I've had to integrate with MS Flow to add blank rows just to force a re-calculation for countdown timers and such.
nested if statments, and(), isblank()
something like
=if(AND(TODAY()-StartDate1>15, isblank(CompleteDate1)),"Red",if(and(Today()-StartDate1>10, isblank(CompleteDate1)), "Yellow","Green"))
I only get green balls, including in the blanks.
I have attached an example of my sheet
Try this modification which is looking at whether Corrections complete is blank,
=if(AND(TODAY()-[Due Date to respond]@row >15, isblank([Corrections Complete]@row)),"Red", IF(and(Today()-[Due Date to respond]@row>10, isblank([Corrections Complete]@row)), "Yellow","Green"))
Or this modification that is looking for a 0 in the corrections complete.
=if(AND(TODAY()-[Due Date to respond]@row >15, [Corrections Complete]@row = 0),"Red", IF(and(Today()-[Due Date to respond]@row>10, [Corrections Complete]@row=0), "Yellow","Green"))
=IF(AND(ISTEXT(Location@row), ISBLANK([Completed Column]@row)), IF([Start Date]@row <= TODAY(-15), "Red", IF([Start Date]@row <= TODAY(-10), "Yellow", "Green")))
Give this a whirl...
Mike's looks like it should work as well.
I have worked the formula a little differently.
Red ball if past due date, Yellow if within 5 days of due date, Green if marked complete.
However I want the RYG column to stay blank if the date received column is blank. How do I write that?
Here is my formula so far.
=IF([RESPONSE COMPLETE]1 <> 1, IF(TODAY() - [DUE DATE TO RESPOND]1 > 0, "Red", IF(TODAY() - [DUE DATE TO RESPOND]1 > -5, "Yellow")), IF([RESPONSE COMPLETE]1 = 1, "Green"))
=IF([RESPONSE COMPLETE]@row= 1, "Green", IF(ISDATE([NOTICE RECEIVED]@row), IF([RESPONSE COMPLETE]@row= 0, IF([DUE DATE TO RESPOND]@row < TODAY(), "Red", IF([DUE DATE TO RESPOND]@row> TODAY(-5), "Yellow")))))
Give this a try.
Perfect!!
Thank you
Happy to help!
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…