Resource Allocation

edited 12/09/19 in Archived 2016 Posts
03/30/16 Edited 12/09/19

Can you assign Resource Allocation for the entire project vs. only assigning per task on each line with % allocation

 

Shanett is only 50% on the prj

Sally is 100% on the prj

Popular Tags:

Comments

  • J. Craig WilliamsJ. Craig Williams Top Contributor

    I believe, Shanett, that you have to do this per task (row).

     

    To make it quicker, filter on Shanett and copy/paste the 50% to all the tasks allocations.

     

    Craig