How can I allocate the resources in single task when I have multiple task owners or multiple Task managers?
Best Regards
Saqib
Hi Saqib,
To use Resource Allocation for multiple people for one task you'd need to have the task on multiple rows.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
We need this functionality - I have tasks in my plan that involve more than one resource, for instance, a meeting. If I have a kickoff meeting, I want to show who has to take time to attend that meeting. My plan is already 900+ lines, I would be challenged to repeat a task 5-6 times just to account for the time everyone takes to do that task.
I would like Smartsheet to adjust duration (not work) when I add a second or third resource to the one task. This would save so much time.
I understand if I add more than one resource to a task, it negates tracking time at all.
Thank you
I agree with Mary, this would be a valuable feature and something that most other scheduling tools offer (e.g. MS Project). It would be necessary however to allow for the effort (i.e. hours) of each stakeholder to be adjustable. The sum total could then be shown in the main schedule view.
This discussion was created from comments split from: I am an editor on a smartsheet but can't edit the sheet.
Good afternoon! My company works closely with another ambulance service, Company B. Both companies have a Smartsheet Enterprise plan. I have created a workspace that I need members of Company B to edit. Do I need to make them members on my account if they are already members on their account? Or do I just need to add their…
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…