Hi,
How can I allocate the resources in single task when I have multiple task owners or multiple Task managers?
Best Regards
Saqib
Hi Saqib,
To use Resource Allocation for multiple people for one task you'd need to have the task on multiple rows.
Would that work?
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
We need this functionality - I have tasks in my plan that involve more than one resource, for instance, a meeting. If I have a kickoff meeting, I want to show who has to take time to attend that meeting. My plan is already 900+ lines, I would be challenged to repeat a task 5-6 times just to account for the time everyone takes to do that task.
I would like Smartsheet to adjust duration (not work) when I add a second or third resource to the one task. This would save so much time.
I understand if I add more than one resource to a task, it negates tracking time at all.
Thank you
I agree with Mary, this would be a valuable feature and something that most other scheduling tools offer (e.g. MS Project). It would be necessary however to allow for the effort (i.e. hours) of each stakeholder to be adjustable. The sum total could then be shown in the main schedule view.
I use Smartsheet for our audit process. It has worked wonderfully all year but a new set of audits just came in and for whatever reason my team has lost the ability to check the completed check box in the sheet. I have checked to make sure the column is not locked, upgraded their permissions to admin. No luck. Screenshot…
We have multiple projects for 150+ countries and we want to create a heatmap style grid to track which project is live in which country. Ideally, we want to convert this grid into a timeline, what would be the ideal way to create this smartsheet?
I'm using a sheet for a project plan. I have a % Complete column and a manual dropdown column for Status (options are Not Started, In Progress, Completed, At Risk, etc.). I want to change the Status column to "Complete" when the % Complete for a task is changed to 100%. Screenshot of my automation set-up is below. Can…