i am trying to build a construction timeline for a project. and i need to use different dependency time frames for different vendors in the same spreadsheet. for example:
Permitting works on a business work week schedule. so Mon-Fri no weekends and no holidays.
However the GC has agreed he wiil complete his work in exactly 120 from his starting day, meaning he will work days, weekend, holidays so to finish this job. so how do I change his dependency settings for just his time frame. the one part of the Gant chart would work off of a work week schedule of monday -Friday and his 4-5 rows needs to calculate based upon 120 calendar days
please help