Hi - I have been using reports for a few months and just recently created a few Baseline reports to monitor Project Schedule changes. I have followed the SMARTSHEET method of creating the baseline and creating the report.
My issue is that the report will not draw from the baseline schedule. I tried just by itself and no data is pulled into the report. Yet clearly the data is there and so I am stumped on why.
I have deleted the report and the baseline sheet twice and rebuilt yet to the same result. 2 days ago I did this for another project and it works fine.
Comments
-
+1 from me.
Looks like a bug to me.
In my case it's a sheet with data linked from a "master sheet". Everything is there, but the report shows only the first 2 rows.
Projektmanagement Professional in Frankfurt am Main, Germany
-
That's what I thought too but becasue I did this before and it worked I thought maybe something else. Will try on another project schedule to see if its just this particular schedule.
-
Projektmanagement Professional in Frankfurt am Main, Germany
-
Thanks for the link. Today it's now working.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives