Hi,
I have lots of sheets with different stakeholders who update these sheets, I want to check which row items have not been updated after their due date or Actual End date.
How can I schedule report like that?
Is there anything specific they would change or do you just want to know if anything changed?
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? That would make it easier to help. (share too, andree@getdone.se)
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I have a report that is referencing a control center program. Other users that are setup as leads on the program and have the same admin permissions I do are able to edit the Group, Filter, Summarize and Sort settings of this report, but I can not. When I click the Columns button it just says "Loading" and even if I leave…
I wish to ADD the following to my existing formula: [Reporting Period]@row="Jan", "Jan" [Reporting Period]@row="Mar", "Mar" [Reporting Period]@row="May", "May" [Reporting Period]@row="Jul", "Jul" [Reporting Period]@row="Sep", "Sep" [Reporting Period]@row="Nov", "Nov" Here is my current formula: =IF(CONTAINS("-",…
I have 165 projects in the portfolio, each with 5 gates and ~120 steps in a project. As an example if a project has successfully passed gates 1&2 and is coming up on gate 3 review, I want to be able to see the rollup at the portfolio then "zoom in" to see the project plan details for a specific project and gate 3. With my…