Dependency from a cell on another sheet
Hello,
I run my manufacturing jobs on Smartsheet.
I have one sheet with multiple projects on it, Parent row per project and tasks indented
I have a few milestone dates in each project for equipment arriving (this date is linked from a shipment tracker) which other task tasks within the project are dependent on before the project can start, but don't necessarily start when the day the equipment arrives. but a problem I have is the overall project start date goes by the first date (equipment arrival date) which isn't actually the date the project starts, so the overall duration of the project is incorrect, meaning i cant measure how long the project actually took
- Is there any way i can make a task dependent on milestone on separate sheet?
- Or is there a way that i can make the project start date (on the project parent row) start from the date the work actually starts, not from a milestone?
I have attached a screenshot with an example
At the moment when i look at look at my projects in Gantt or calendar view, the length of the project is far longer is inaccurate and looks really messy.
Comments
-
Hi Abby,
It's not currently possible to create cross-sheet dependencies or to manually change the start or end dates in a parent row when dependencies are enabled. When you have a moment, please submit a Product Enhancement Request, to let our Product team know you would like to have these functionalities within Smartsheet.
If needed, more information on the parent roll up functionality can be found here: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives