Changing linked cells to point at a new sheet en masse
Hi
I have a task list that has dates linked in from a separate calendar sheet. We have 12 calendars (1 per month) but only the 1 task list. Is there a way to change all the links in the task list to a new calendar sheet rather than one by one relinking each one?
Thanks
Comments
-
Hi Andrea,
Yes, there is. If you select the range of cells you want to link from and copy them and then without leaving the tab you're in, go to the sheet where you want the linked values and right click in the first cell of the range and select Paste Special and Links to copied cells.
Would that work?
Have a fantastic week and let me know if you have any questions!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Thanks for this, I tried but even after highlighting the range of cells to "paste special" to it only pasted the link in the first cell of the range.
-
Happy to help!
It will paste the same range as you copy. If you copy ten cells, it will paste ten cells, and you only need to select the starting cell.
Did you get it to work?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.7K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives