In MS Project there's a column called "Work".
that if I write for example for an X task, 6 days in the work column, and assign 2 persons on this task >> the duration will be 3 days.
How can I have it in your gantt?
G.
Thanks for the question! At the moment, duration is not tied to resources in Smartsheet. Check out this thread where users are having a conversation about this topic: https://community.smartsheet.com/discussion/it-possible-assign-task-multiple-people