IF(And formulas to count late dates
I would like to create a formula that measures the health of a project (Red, yellow, green) with missing dates:
Expected Date (June 6, 2019)- I assign that date to the vendor
Scheduled Date (this is expected within 5 days of assigned expected date)- this is filled in by vendor
Completed Date (this is expected within 5 days of scheduled expected date)- this is also filled in by vendor
What I would like to have the health colors change when the vendor hasn't placed the dates in to call out the health of that task (also highlighting that it's late).
I am assuming that I would have to have a few health titles; ie. Beginning Project Health, Completing Project Health, etc.
Thanks
Jennifer
Comments
-
Hi Jennifer,
Can you describe your process in more detail and maybe share the sheet(s) or some screenshots? (Delete/replace any confidential/sensitive information before sharing) That would make it easier to help. (share too, andree@getdone.se)
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives