i use baseline start/finish columns and scheduled start/finish columns. The start column uses predecessors but I also update the start/finish columns for actual start/finish. The downside to updating them is that i lose my predecessors (they are deleted when I manually change start/finish).
Is there a SmartSheet best practice for preserving the predecessors?
My initial thoughts (though this seems a bit unwieldy) is to have three sets of dates:
- Scheduled Start / Finish
- Baseline Start / Finsh
- Actual Start / Finish.
Only the actual start/finish would be updated unless a start/finish were to change schedule, in which case I would add (or adjust) lag in the predecessor to take into account the change. This isn't a perfect record of the predecessor but at least they aren't wholesale deleted.
Any thoughts?
Thanks,
AEG