Hi, I'm seeking to round down a start date so it begins at the beginning of that day. Within my project plan, there are a number of partial day tasks (0.25d, 0.50d) that influence the successors, resulting in "Start Dates" being midday. I'd like to round down the start date so that a simple 1.0d duration starts and finishes in the same day? Apart from manually adjusting the task to 0.75d or 0.50d, is there another solution? Thank you very much in advance for your suggestions.