I've done some research, so I'm pretty sure I already know the answer. I have a project with a hard completion date. I would like to have any subtask scheduled backward from the completion date. Can that be done in Smartsheet?
Hi,
There is a Template called: Project with Hard Deadline and Gantt that probably is what you´re looking for.
Hope that helps!
Did it work?
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Andree,
Please enter the link for this Template or information you found. Your comments are useless to everyone searching. This is not the best website for searching and finding correct answers at the top of the list. On these community boards we need to be accurate in the links to point people in the right direction. Thanks.
At the time of my post, I don't think it was possible to link to the templates but now it is so here you go:
https://app.smartsheet.com/b/home?sc=mjjH3-k10qQ%2Cm9FH33U15fo%2C1
I hope that helps!
Workflow Consultant / CEO @ WORK BOLD
This Template is located in the SOLUTION CENTER
Go To Solution Center
Enter Search : Project with Hard Deadline
You will see the Single Project Template Called
"Project with Hard Deadline and Gantt"
Click on it and it will appear in your SmartSheet Collection
Not much to look at but at least it can start a person in the right direction for entering a Deadline Date and the remainder of items get scheduled using predecessors with SF with task below.
My link above is the direct link to open a copy in your account.
Here's a link to the Solution Center page with that specific template.
https://www.smartsheet.com/marketplace/templates/project-hard-deadline-and-gantt
I'm trying to create a graph chart that captures monthly count of records by divisions (Northeast, West and Central) that should be stacked with a legend displaying each by different color like a presented in Excel. When I attempt to duplicate the process in Smartsheet I receive the following results. In Excel, I created…
Good afternoon, I am trying to utilize Linked Dropdown Columns for a manual process we have. We have many sheets that use a "Client Name" column with a dropdown list. Whenever a new client comes on or exits, we have to manually update every sheet that has a Client Name column and update the dropdown list. We do not have…
This should be straightforward information but I can't find it anywhere. How do the Automation triggers work for attachments? I assumed: An attachment is Added = New attachment An attachment is Changed = New version of existing attachment. But I just had an 'Added' attachment notification trigger when I uploaded a new…