Gantt chart representation on Dashboards

Kirk Preston
✭✭✭
I know how to make a report so that I can show a timeline in a dashboard. The strange thing is that the Gantt chart does not show dependencies or % complete, even if I include those columns. Is this something that should work currently or something that has not yet been implmented?
Also, "Dashboards" does not appear to be a choice under "Functionality" when submitting a discussion.
Kirk
Tags:
Comments
-
Hello,
Reports don't currently display the overlaying grey bar on each task or dependency relationships in the Gantt chart. When you have a moment, submit a Product Enhancement Request to let our Product team know that you'd like to have this functionality in Smartsheet.