Sign in to join the conversation:
I would like the column "Done" to be checked automatically if the % Complete is changed to 100%. I am using the formula below which is not working:
=IF([% Complete]3 = "100%", 1)
Any suggestions?
If your % Complete column is formatted to be a percentage, you will need to replace "100%" with 1 (no quotes).
=IF([% Complete]@row= 1, 1)
thank you so much!!! it worked
Happy to help!
Smartsheet stores percentages as a fraction of 1, so
100% = 1
75% = 0.75
50% = 0.5
25% = 0.25
0% = 0
and everything in between.
I am trying to setup a sheet that can project dates decades into the future. I want a formula that can look the date in the row above, check to see if it's annual or quarterly, then add the appropriate number of months to each row. While testing the formulas, I keep getting stuck on how to add one year (12 months) to each…
Good morning, I have a document that I download from an outside source. I have set up a data shuttle to import it into Smartsheet. I have other sheets that need to be updated based on the info in the imported sheet. None of the formulas are working once a new file is imported. Details: Sheet imported through Data Shuttle…
I have a form adding new rows to my smartsheet but it doesnt add the next number in the primary key, is there a way to do this?