Delta/Slippage Formula
I can't seem to get the right formula together in my Active Projects Master Schedule to show the Delta/Slippage in the construction schedules.
I have individual columns for Original Finish (Date), Current Projected Finish (Date), and Change Order (CO) Days that are populating dates and numbers with cell linking from the individual project schedule sheets.
I know the formula for the Delta/Slippage needs to be: Original Finish + Current Projected Finish - Change Order (CO) Days = Delta/Slippage
Any ideas on how the formula should be put together in Smartsheet? All my attempts end in error messages.
Comments
-
If you wanted to use working days instead of calendar days, use =Networkdays instead.
-
@Paul. I am unable to add two dates together to get a number. Is this something you've done before? I have to use netdays to get the number of days between two dates.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- 10.8K Get Help
- 65 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.6K Ideas & Feature Requests
- 56 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives
Check out the Formula Handbook template!