Prevent Formula Overriding
Hi there!
I have a column set up to indicate Task Progress (can choose from dropdown: Not Yet Started, In Progress, Nearing Completion, etc.) but also would like it to automatically mark "Complete" if another column (checkbox formatting) has a marked checkbox.
The issue I'm having is that the formula erases if someone chooses a value from the dropdown/types in their own. This means that when the task is checked as complete in the checkbox column, the Task Progress column does not update to "Complete" and the user has to manually change it.
To try to prevent this- is there any way to set it to where a formula is not overridden by manual input? Thank you!
Comments
-
Hi Madison,
Unfortunately, it's not possible at the moment to have a formula and also change values manually, but it's an excellent idea!
Please submit an Enhancement Request when you have a moment.
A possible workaround would be to have a formula that changes the status referencing the date and other cells.
If you still want to be able to change the value manually, then you could use the third-party service, Zapier, to change the value to complete, and it's not dependent on any formula.
Would one of these options work? Is Zapier an option for you?
I hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Hi Madison,
As Andree stated, this isn't currently possible. If you want to automate the process you have to automate the entire process or not at all. Any manual adjustment of a field that has a formula in it, will overwrite the formula and negate it. To work around this our team automated the entire process. We created Actual Start and Actual Finish date columns and then used the following formula to indicate the status of our project.
=IF(AND(Isblank([Actual Start]@row), Isblank([Actual Finish]@row)), "Not Started", IF(ISBLANK([Actual Finish]@row), "In progress", IF(ISDATE([Actual FInish]@row), "Complete")))
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 488 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!