Changing the # of work hours in a day.
Comments
-
Hello Mike—You're correct, as long as dependencies have been established in your sheet, changing the working hours may push dependent tasks up to the previous working day. These calculations are based on the type of depenendency and/or lag time established.
If dependencies haven't been established in the Predecessors column then dates likely won't be adjusted if you change your working hours.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives