Hi,
All my project sheets are all set up with project, status, start date, end date, duration, %complete and predecessors. I also have a checkbox column to mark when a task is complete.
I'd like to format my % complete column so that it auto-calculates how much of a task has been done based on the start and end dates.
I'd also like to format my status dropdown column so that if I select the complete check box, the status auto-updates to 'Complete' and the %complete column is marked at 100% (irrelevant of the start/end dates).
If there's any way to format the project headline (i.e. parent row) so that the status changes to 'Complete' when all child rows are marked as such and if all child items have the complete box checked so does the parent row; that would be great too.
Thanks