Is it possible to add a delay to a task if it doesn't have any predecessors ?
I have few tasks in my sheet, which are not independant of other tasks. The dependencies have been swtiches on in the gantt view. Is it possible to add a delay to these tasks without manually changing the dates ?
Answers
-
Hi,
Yes, if I've understood your question correctly.
You'd use Lag Time.
Lag Time and Lead Time
To represent a period of inactivity or overlap between the predecessor and dependent, you can use lag time. For instance, entering 1d into the “Lag (days)” field for a Finish-to-Start dependency causes the dependents to start an additional working day after its predecessor finishes. To schedule the dependents to start before the predecessor finishes, use a negative number (for example, -1d) to create lead time.
NOTE: Lag and lead time can be entered in increments of weeks, whole working days, partial working days, hours, minutes, seconds, milliseconds, or a combination (in similar fashion to the duration examples above)
Would that work?
I hope that helps!
Have a fantastic day!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
✅Did my post help answer your question or solve your problem? Please help the Community by marking it as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Greetings,
Thanks for the prompt reply. I made a spelling error. I meant to ask, if the tasks ARE Independant, then how can we show a delay without manually changing the dates.
Thank you
-
Happy to help!
I have an idea!
Can you describe your process in more detail?
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Greetings,
So we have some tasks, for example Task B is not dependent on Task A. In case there is delay in the end date, how do we show that in the predecessor column, without manually changing the date section ?
Thank you
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives