automation - mark Main Task 100% complete and Status=Complete when all sub tasks are complete

Hi, i'm a newbie and have a question about Smartsheet.

I was wondering if Smartsheet can do the following: I would like for the parent task to be marked 100% complete and Status=Complete when the sub-tasks are 100% complete and Status=Complete. For example, I have a task call "Deploy Server" and there are 3 sub tasks underneath it ("Task 1,"Task 2",Task 3"). When the last sub-task has been marked 100% and Status=Complete, the Main task called "Deploy Server" is marked 100% and Status=Complete.

Is there a way to do that?

Thanks in advance.

Best Answer

«1

Answers