Combining Two Formulas in One Cell (NETDAYS and Addition)

Options

Hi everyone,

I am looking to combine two formulas in one cell (one to calculate number of days; one to calculate completion date, using calculated days). The information below was provided to me by my supervisor to use, but I have been struggling to come up with a solution. Here is the information:


Formula: First Product Date (09/01/20) - 30 calendar days (manufacturing, sub-assembly, etc.) - Lead Time (09/01/21)


My initial approach:

NETDAYS([First Product]1, [Lead Time]1) - 30 = 336 days

[First Product]1 + 336 = 08/03/21


The first formula calculates the total days of development and production, then that calculated amount is added to the first product date to roughly guess on what specific date should I expect the project to be completed. Dates will change, but this is just an example.


Any and all help is greatly appreciated!

Best Answer

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!