Automatic Duration calculation from 2 Predecessory
Hello
I have a Task B that cannot start before Task A was finished and that should finish the same time as Task C.
When I enter 2 predecessors for B, namely that Task A has FS and Task C has FF, the smartsheet always takes into account only one of the Predecessors and puts the duration on 1d automatically (see screenshots).
However, I want the duration to be flexible but I want the 2 predecessor conditions to be fixed! So when I would change the start date of Task A, the duration should change automatically acccording to the 2 predecessors conditions.
How can I do that??
Thank you very much!
Best regards
Tibor
Comments
-
You would have to make sure the duration for Task A stays 14d. THat way when you move the start date of Task A, it moves the finish date of Task A which in turn would shift the start date of Task B.
Based on your provided screenshots, it is populating correctly. Task B starts after Task A finishes and ends when Task C ends.
-
Hi Paul
Thank you very much for the quick answer.
I want Task B to start at 15/1/21, right after Task A, without any lag.
But when I put 15/1/21 manually as a start date, then it wont adjust anymore when I change Task A...
Do you know how I can fix the start date right after Task A has ended without lag?
Thanks!
-
My apologies. I am used to a different date format, so it had me all kinds of discombobulated...
What is the relationship between Tasks A and C?
-
Oh yes, sorry for that! :-)
Task A and C have no relationship.
I simply want to put Task B right after A and to finish with C - duration does not matter and should be flexible.
Thanks again!
-
What if you set Task A to have a Predecessor of Finishing before Task B starts?
-
I just tried, it still defaults the duration of Task B to 1 day...
Also for some reason it does not give the end date of Task A anymore...
I think it is not possible to leave the duration flexible with dependable dates...
But thank you anyways for the help!!
-
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives