Hello,
I'm fairly new to Smartsheet, but have been using MS Project for a while and pretty comfortable with project management tools. I have a sheet that is over booking resources, I have no clue why! I have two tasks that have a duration of 3 days requiring the same resource, they are both dependent on an earlier task. Smartsheet is scheduling both tasks to be done over the same 3 day period! I have resource managment and dependencies enabled, and have set a 5 day work week with 8 hour days.
I assume/hope I'm just missing some obvious setting!
Thanks,
Maureen