:% Completion Drop Down freeze
Comments
-
Hello Henry,
If you're using dependencies on your sheet, there isn't a way to automatically update the % complete based on a dropdown value. More on the dependencies functionality is available in our Help Center: https://help.smartsheet.com/articles/765727
If you're not using dependencies on your sheet, it's likely that you were using formulas to populate the % complete values based on the dropdown value. You may need to recreate the formulas if they were deleted. Details on using formulas can be found here: https://help.smartsheet.com/articles/775363-using-formulas
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives