:% Completion Drop Down freeze

We are unable to use the drop-down option to update the % completion of our projects but it allows us to manually update it. It has being like this for about a week. How do I fix it?
Comments
-
Hello Henry,
If you're using dependencies on your sheet, there isn't a way to automatically update the % complete based on a dropdown value. More on the dependencies functionality is available in our Help Center: https://help.smartsheet.com/articles/765727
If you're not using dependencies on your sheet, it's likely that you were using formulas to populate the % complete values based on the dropdown value. You may need to recreate the formulas if they were deleted. Details on using formulas can be found here: https://help.smartsheet.com/articles/775363-using-formulas
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.2K Get Help
- 452 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives