Connect with peers, share your expertise, and inspire what’s next in Smartsheet — from proven practices to practical how-to insights from fellow users and product experts.
Sign in to join the conversation:
The posts in this section are historical and no longer monitored for accuracy. If this discussion interests you and you'd like to join in, please visit the active Community to post and engage.
I am making one for a schedule in another country and I want to be able to change that without changing the holidays for all of my spreadsheets.
Hello Teresa,
You can change them on the sheet level with the steps in our Help Center: https://help.smartsheet.com/articles/516392-defining-working-non-working-holidays-on-a-project-sheet
Teresa,
Be aware that a change made by your SysAdmin to the default holidays only effects new sheets, not existing ones and requires a Team license or higher.
From:
https://help.smartsheet.com/articles/1159581-global-account-settings-team-business-enterprise-
Click Edit next to this heading to configure the length of working days, as well as designate non-working and holidays, for purposes of scheduling your projects. Your selection will be applied to all new sheets created by licensed users on the account. Existing project sheets won't be affected by your changes. Learn more about how these settings impact project scheduling in our article on Designating Working, Non-working & Holidays on a Project Sheet.
Craig