% Complete in Project Template seems to be off.
Working in a Smartsheet Project Template. I've put in my % complete info for each WSB row. The Parent % complete is reporting back 21%, while a selection of the rows shows that the average should be 19%
Does anyone have a logical explanation for this?
Best Answer
-
Hello @Michael Macygin
The reason you're seeing a different % Complete in the parent row is due to the Parent Rollup Functionality of Project sheets. The % Complete on the Parent row will calculate a weighted percentage based on both the Duration and % Complete entered on each child row.
For example, if a child task is only 1 day long and it's 100% complete, but a second child task is 50 days long and is 0% complete, then the overall Parent will take those durations into account. Instead of an inaccurate 50% complete, it would show just 2%, since the first task is such a short one.
Our Help Center article on Parent Rollup Functionality has more details on this, see here.
Hope this helps!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Answers
-
What is the formula being used to calculate these percentages, particularly for the parent row?
-
I'm not relying on a formula here. The Parent Row is being auto calculated by the Project Template I'm using. I'm just placing % Complete data in the Children rows and allowing the template to auto calculate. As a matter of fact, when I try to make any changes to % Complete cell in a Parent row, I get the the following message from the platform.
-
Hello @Michael Macygin
The reason you're seeing a different % Complete in the parent row is due to the Parent Rollup Functionality of Project sheets. The % Complete on the Parent row will calculate a weighted percentage based on both the Duration and % Complete entered on each child row.
For example, if a child task is only 1 day long and it's 100% complete, but a second child task is 50 days long and is 0% complete, then the overall Parent will take those durations into account. Instead of an inaccurate 50% complete, it would show just 2%, since the first task is such a short one.
Our Help Center article on Parent Rollup Functionality has more details on this, see here.
Hope this helps!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Hi
I had a similar issue as the plan was showing 0 or 100 and I knew there should be a different number in the roll up.
I needed to ensure that the start and end dates were added to the plan in order for this to work.
Hope that helps.
Purnima
Purnima Gore
Cierr Limited
Your Time is Important, you want to Stay on Track, We can help you use the Right Tools
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 495 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!