Is there any way to stop a user to complete a task if this task predecessors are not complete?
I have a project 2 big sections: Project related tasks and Product related tasks.
The project related tasks contains "project" milestones.
Each product development contains Product milestones.
I need to complete the milestones for the project ONLY if the "corresponding" product milestones are completed.
SMARTSHEET SHEET
- PROJECT TASK
- PROJECT MILESTONE 1 - Predecessors: Prod1 Milestone1, Prod2 Milestone1
- PROJECT MILESTONE 2 - Predecessors: Prod1 Milestone2, Prod2 Milestone2
- PRODUCT TASKS
- Prod1
- - Prod1 Task1
- - Prod1 Task2
- - Prod1 milestone1
- ...
- Prod 2
- - Prod2 Task1
- - Prod2 Task2
- - Prod2 milestone1
- ...
Then i need to be able to complete the task PROJECT MILESTONE 1 only if the taks Prod1 milestone1 and Prod2 milestone1are completed (its predecessors)
Thanks a lot.