Link dependencies between sheets
Hello everyone,
Do you konw if it is possible to link dependencies between two sheets ?
For example I have a sheet for project A, and in this sheet I have an activity that has a predecessor from another sheet for project B ?
I don't think it is possible but if you have some answers that would be helpful.
Thank you,
Corentin
Answers
-
Dependencies works within the same project.
So regarding this, I would say that Project A is part of Project B.
Or you could also have Project C that is equal B + A where you'll be able to create dependencies between both projects.
Then use some INDEX/MATCH to return dates for project A & B, but it doesn't seem to be really useful.
-
Hello @David Joyeuse ,
Thank you for your help.
Effectively I need to have two separate sheets, one for project A and one for project B.
I think that having a project C is complex because I will have to get back all the data automatically
I saw that I can't put formulas in dates column that are link with a Gantt chart..
Thank you for your help anyway,
Corentin
-
The ability to create and maintain multiple projects that are dependent upon each other (a task in one sheet affects the calendar of a task in anther sheet) is a critical feature allowing users to build many projects.
I have over (30) projects that relate to each other and I have to build one immensely large project is a bit crazy...
Please provide this option ASAP.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.9K Get Help
- 441 Global Discussions
- 153 Industry Talk
- 501 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 79 Community Job Board
- 511 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 37 Webinars
- 7.3K Forum Archives