Hello,

I am wondering if there is a way to automate/semi-automate adding holidays to project settings.

For example, is there a way to indicate 12/25 will be a holiday regardless of the year, so that as time goes on new Sheets will always take into account standard holidays?

Thank you,

Dan

👨🏼💻 Dan Palenchar | School of Sheets Solutions Consulting | Smartsheet Aligned Gold Partner

If this helped, help me & the SSC by accepting and reacting w/ 💡insightful, ⬆️ Vote Up, and/or ❤️Awesome!

PS - If you have a follow up response tag me @SoS | Dan Palenchar so I get notified of your reply!

Answers

  • Mike Wilday
    Mike Wilday ✭✭✭✭✭✭
    Options

    You can't designate recurring days, but your smartsheet admin can add a comma-separated list of holidays as far into the future as they want by navigating to:

    1. Admin Center from the user menu

    2. Working Days

    3. Enter a comma separated list of holidays going as far into the future as necessary.