Save as New - not carry over alerts?
Hi there. It appears that when use Save as New to copy a project plan with all connections, the alerts set up are not transferred over. Is that correct? I saw a thread about this in 2017 and am wondering if it was ever solved?
Thanks!
Best Answer
-
Thank you! Appreciate the help.
Answers
-
There are multiple checkboxes available when saving as new to determine what gets copied over and what does not. Clicking on the arrows indicated below should make these different checkboxes available.
-
Thank you! Appreciate the help.
-
Happy to help. 👍️