Trying to calculate an "on this day" capacity
Hi There,
I have a master sheet of multiple projects. I am trying to work out how an allocated resource can show if it is over capacity in a column - similar to the resource view but so it shows in the sheet itself.
So If I have
Task
Start Date
End Date
Duration
Assigned to
Allocation %
Hours per day
I want to look up the allocation % between the start date and end date for [assigned to] and then do a lookup of all Rows where assigned to resource is mentioned and calculate the allocation %
1 Jan - 5 Jan, Task 1, Resource 1, 50% allocation - Column that shows Total allocation 150%
1 Jan - 3 Jan, Task 2, Resource 1, 100% allocation - Column that shows Total allocation 150%
I just cannot work out the formula to do this
Thanks,
Martin
Best Answers
-
Hi @Martin Hammond
Hope you are fine, as per your question the following formula will do what you need
=SUMIFS([Allocation %]:[Allocation %], [Assigned to]:[Assigned to], [Assigned to]@row)
but as a planning Engineer, i can say to you this is not correct because in the above example you can see that the Total allocation for Resource 1 is 150% only from ( 1-Jan To 3-Jan ) but from ( 4 To 5 Jan ) his allocation is 50% only. so you need to think in a different approach.
maybe you need to do a summary table in a helper sheet contain all Resource in your project in a rows and the day of the month in the columns and calculate for each day if the Resource is overallocated or not.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
If it is of help to anyone I worked out how it correctly displays for me:
=SUMIFS([Allocation %]:[Allocation %], [Start Date]:[Start Date], >=[Start Date]@row, [End Date]:[End Date], <=[End Date]@row, [Assigned To]:[Assigned To], [Assigned To]@row)
Answers
-
Hi @Martin Hammond
Hope you are fine, as per your question the following formula will do what you need
=SUMIFS([Allocation %]:[Allocation %], [Assigned to]:[Assigned to], [Assigned to]@row)
but as a planning Engineer, i can say to you this is not correct because in the above example you can see that the Total allocation for Resource 1 is 150% only from ( 1-Jan To 3-Jan ) but from ( 4 To 5 Jan ) his allocation is 50% only. so you need to think in a different approach.
maybe you need to do a summary table in a helper sheet contain all Resource in your project in a rows and the day of the month in the columns and calculate for each day if the Resource is overallocated or not.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Thanks Basam that has helped a lot and given me food for thought on how to display capacity
-
You are welcome
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
-
Actually taking a look it the formula doesn't contain the date ranges so I do not think it would be correct, it would repeat the same sum regardless as it would not know what date range to search in
-
If it is of help to anyone I worked out how it correctly displays for me:
=SUMIFS([Allocation %]:[Allocation %], [Start Date]:[Start Date], >=[Start Date]@row, [End Date]:[End Date], <=[End Date]@row, [Assigned To]:[Assigned To], [Assigned To]@row)
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 302 Events
- 33 Webinars
- 7.3K Forum Archives