I am a bit concerned with tracking project progress with SMARTSHEET.
I understand that Smartsheet project planning principle is based on duration, and that way a task wich lasts much is more weighed than a task which takes less time.
But in real life , it is not often the case , to prove this , check my example regarding the construction of a kitchen in concrete structure .
In that case , even if the finishing works take more time than the structure works , the structure works is more costly and require more ressources .
So in this view , completing the structure works means logically that the overall project has high percentage complete , but in my example , when the structure works are over , the overall project is just 31 % complete , that's a non-sense in my contexte .
So I would like to know if someone can suggest me a workaround .