Date Automation is not working
mg3245
✭✭✭
I've got an automation set up in a way that if a row is added, the date gets captured. However, when adding data to a new row, this does not seem to work. I've even waited for 30 + mins since some discussions have mentioned a 'delay' in the automation working (however, I understand that this has now been resolved anyway).
Attaching a screenshot of the automation I've set up and any help would be appreciated.
Tags:
Answers
-
Try changing your trigger to when a row is added or changed and then include when Client changes to any value.
-
Thanks it is working now!
-
Happy to help. 👍️
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!