Can you set a task to ignore non-working days?
Can you set a task to run for a fixed number of days - regardless of non-working time?
For example - I have a 3 day task which is the time it takes for changes to be applied to a User Account (e.g. the addition of new software, changes to security permissions, etc).
This takes 3 days. Weekends and Easter Holidays don't apply to computers! So a change made on Friday morning will be live on Monday morning. But if I put in a 3 day task starting Friday, it will show as ready on Wednesday morning.
If this isn't possible - a request would be to be able to assign a "hard" duration to a task.
"3d" = 3 working days
"3dh" = 3 days (always T+3)
Comments
-
Rob,
Try using elapsed time such as "e3d" in the cell!
Ben
-
Genius! Worked like a charm
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives