The start date in the details section is available for update but the finish date is not. I do have dependencies set for these since we are using resource management on the source sheet. I can change the start date and the duration, but I can't make the start date begin after the finish date. There may be times when soemting gets delayed and needs to be pushed out further.
How can I do the following in the details screen without going to the source sheets:
1: Change the finish date
2: Change the start date to begin after the finish date if the task has been delayed.