Hi there
If I'm correct, Smartsheet only provide the "Time Duration (i.e. Days)" as the basis for Porgress Measurement in Project Plan. It's good in a way, but not that professional.
For now, I have to set up a column for uploading the budget mhrs for each tasks (say 200 to 300 tasks for a classic project) and use it as the weight factor, i.e., the basis for the progress measurement. And the actual % is based on the hours as well. Say, I spent 50% of the time of the task, I may achieved 80% of the budget mhrs or vice versa 40% of the budget mhrs.
So, the question is: how could I show this type of Actual % in the bar in Gantt View rather than the default one based on duration?
Thanks
Regards
KJ