When I'm building a Gantt chart, I want to enter task, duration, and have the bar show up on the gantt chart so I can drag a dependency to it. It seems I have to enter a start date each time, THEN a bar shows up, then I can create a dependency.
Is there a way to enter a default date on each new task without having to manually enter the start date?
Answers
-
No. There is no way to have a "default" date automatically entered. You will have to enter a date for each task as added.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.6K Get Help
- 371 Global Discussions
- 203 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 447 Show & Tell
- 29 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives