When a date is reached

Hi all, i am trying to use the Automation feature to send a weekly reminder email to 'specific people' using the 'When a date is reached' trigger.

However the test reminder i have setup for myself i can't seem to get this running. Is this because there is no specific cell value within the smartsheet that is prompting the workflow to run?

I think it must be simple i am missing, but havent managed to spot it after a few sessions trying.

Feedback apprecciated!

Thanks and have a good day

Hugh


Answers

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    edited 09/10/21

    Hi @Hugh Crane

    I hope you're well and safe!

    Ensure that you've checked the Sheet Change Notification Settings box to Include my changes in sheet notifications in your Personal Settings (circle/profile in the lower-left corner).

    Did that work/help?

    I hope that helps!

    Be safe and have a fantastic weekend!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.