Duration Column - Contains Units
Hello all.
We would like to use the duration column in a number of our Smartsheet calculations. However, we noticed that the "units" appear (in our case, it seems to be "d" for days)
Example: Start Date: October 25, End Date: October 27. This returns Duration: 3d
Is it possible to remove the d in the Duration column to be just: 3? We would like it to be a numeric column only (no UoM).
If this can't be done, is the only option to do our own calculation between two dates in a new column (e.g. Duration2)?
Answers
-
If you are using the duration column as part of the dependency settings, then the data is stored on the back-end as a numerical value. You should be able to go ahead and run your calculations on that even though the displayed value shows a "d".
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.7K Get Help
- 371 Global Discussions
- 203 Industry Talk
- 436 Announcements
- 4.5K Ideas & Feature Requests
- 137 Brandfolder
- 129 Just for fun
- 129 Community Job Board
- 448 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 282 Events
- 32 Webinars
- 7.3K Forum Archives