Predecessors and Critical Path
Hello,
I work in the events industry and use Smartsheets for our project plans.
As we work to a set date (Event Date) and the post-work afterwards (usually completed within 6 wks), our Predecessors tend to be minus (i.e. event date - 20wks to scope venue). This also affects our critical paths, usually rendering the critical path useless.
I realise this is probably not the best way to set up our plans, but I don't see how we can do this?
Would you have any advice?
Thanks
Aimee
Answers
-
@Aimee Colton I have built multi-month projects where the key date was "Store Grand Opening" and every milestone before that date was a predecessor as you described (GO - 20wks, etc.)
That should work for you, but maybe I missed your question.
** I built groups of tasks (usually based on departments). Each department identified how far before Opening they needed to start. The first task for that department was GO - [start date]. Then the subsequent tasks for that department went forward from there.
The tasks post-GO were built "normally" with predecessor = GO +1wk, etc. as required.
My observation is that the critical path functionality still works fine.
dm
-
Thank you for your comments. Can I check when you say GO-20wks, you mean for example row 200-20wks?
-
@Aimee Colton Yes, sorry for the cryptic note.
"GO" = Grand Opening = the task at a certain row (e.g., row 200).
So the predecessor entry for an earlier task that referenced "GO" would be "200FS - 20w" as you articulated ...
Cheers,
dm
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 459 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 138 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives