Smartsheet Control Center - Resource Management
Hello everyone,
Do you know if there is something existing or planned in order to connect Smartsheet Control Center and Resource Management ? Here is my use case that I imagine :
- I create a project in Control Center (with a project plan in the Blueprint).
- Once the project is created, it automatically creates a project in Resource Management and link the project plan sheet in Smartsheet with the project in Resource Management.
This feature could really help us as today we do not have any choice but to manually do these actions once the project is deployed through SCC.
Thank you for your help,
Corentin
Best Answer
-
Hi @Corentin Dal Farra This capability does not exist in Control Center, simply request for the Control Center Resource Management integration to be enabled. Cheers PPS
Answers
-
The Resource Management panel can be used with sheets created by Control Center (and can leverage Resource Management placeholders assigned ahead of time as part of the template), however, this isn't currently automated and requires a manual step to establish the connection via the panel as you've found.
Please let the Product team know about the use-case you outlined above so they can hear your feedback on the current functionality through this form, here!
Thanks,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
-
Thank you for your answer ! I will do a feature request, and please let me know if this is planned in Smartsheet roadmap or If you have any news about it in the future,
Have a great day,
Corentin
-
Hi @Corentin Dal Farra This capability does not exist in Control Center, simply request for the Control Center Resource Management integration to be enabled. Cheers PPS
-
Hi @Corentin Dal Farra Hi Corentin, sorry I meant to say in my last post that this capability DOES exist in Control Center, just ask for it to be enabled. Cheers PPS
-
Thank you for the answer, I have ask it to be enabled but I think that there is a lack of documentation and guidance about this connexion unfortunately.. Here is my example below :
I have ask the support team for more enablement, please let me know if you have any information,
Have a nice day,
Corentin
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.8K Get Help
- 410 Global Discussions
- 219 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives