Pull hours worked (from Resource Management) to column in a Project Plan (in SmartSheet)?
Brand new user here, so I am climbing the learning curve.
I just created a simple test project in Resource Management. I also created a Smartsheet project plan (i.e., a grid) that matches the Resource Management project. Resource Management is enabled.
For now the project plan includes columns showing the amount of time expected per task (as hours, which was used to create the budget reflected in RM) and the expected duration (in days) for each task.
(And yes to enable full blown Resource Management the project plan also has columns for assignees and allocation.)
I would like the project plan to include a column showing the actual number of hours worked, based on timesheet entries. I'd also like to have a separate column showing the actual number of days worked on the project.
Can I do this in the grid? Or must I do it through a report or some other way?
Answers
-
Hi deanovermont,
For a separate column showing the actual number of days worked on the project, you can use NETWORKDAY function to calculate the worked days with Start-date and End-date as inputs.
For a column showing the actual number of hours worked, based on timesheet entries, I think about using some calculation of Start-time and End-time as inputs.
Gia Thinh Technology - Smartsheet Solution Partner.
-
Thank you, @Gia Thinh. That answers part of my question. I still can't see if/how I can pull data directly from Resource Management.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives