Planned Dates appear on days defined as non-working days in Smartsheet
We have defined holidays and non-working days in the Project Settings, but noticed that Smartsheet still shows several "Planned" Dates falling on these non-working days based on planned durations, instead of pushing these out to the next working day (This also happens for Saturdays and Sundays while we have defined M-F work week).
Is there a way to avoid this from happening?
Best Answer
-
Hi @tariq.shaikh@signspecialists.com ,
You should check the box "Make this the default setting for all users in my account" as below screenshot. This will affect all sheets created from now on. For existing sheets, you should manually set one by one.
Hope that helps.
Gia Thinh Technology - Smartsheet Solution Partner.
Answers
-
Hi @tariq.shaikh@signspecialists.com ,
You should check the box "Make this the default setting for all users in my account" as below screenshot. This will affect all sheets created from now on. For existing sheets, you should manually set one by one.
Hope that helps.
Gia Thinh Technology - Smartsheet Solution Partner.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives