Planned Dates appear on days defined as non-working days in Smartsheet
We have defined holidays and non-working days in the Project Settings, but noticed that Smartsheet still shows several "Planned" Dates falling on these non-working days based on planned durations, instead of pushing these out to the next working day (This also happens for Saturdays and Sundays while we have defined M-F work week).
Is there a way to avoid this from happening?
Best Answer
-
Hi @tariq.shaikh@signspecialists.com ,
You should check the box "Make this the default setting for all users in my account" as below screenshot. This will affect all sheets created from now on. For existing sheets, you should manually set one by one.
Hope that helps.
Gia Thinh Technology - Smartsheet Solution Partner.
Answers
-
Hi @tariq.shaikh@signspecialists.com ,
You should check the box "Make this the default setting for all users in my account" as below screenshot. This will affect all sheets created from now on. For existing sheets, you should manually set one by one.
Hope that helps.
Gia Thinh Technology - Smartsheet Solution Partner.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives