How to set the start date on a given day of week after predecessor completes
If I have a task that can only happen on a Tuesday (e.g. that's when an approval committee meets), and all the predecessors are scheduled to complete the previous Thursday, how do I schedule the task to start on the first Tuesday after the predecessor completes?
Tags:
Answers
-
Hi @mvanderv
You can add Lag Days to dependent tasks by adding that number to the Predecessor cell: +2d
See the bottom of this Help Article: Work with Duration and Predecessors
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!