Open Days in a project
I'm trying to calculate how many days a project stays open base on completion date:
This is the formula I'm using, the problem is counting an extra day if the project is completed.
=IFERROR(NETDAYS([Submission Date]@row, IF(ISBLANK([Completion Date]@row), TODAY(), [Completion Date]@row)), "No Submitted Date")
it was completed in 2 days, but the formula gave me 3 days.
Best Answer
-
Try this:
=IFERROR(NETDAYS([Submission Date]@row, IF(ISBLANK([Completion Date]@row), TODAY(), [Completion Date]@row - 1)), "No Submitted Date")
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Answers
-
Try this:
=IFERROR(NETDAYS([Submission Date]@row, IF(ISBLANK([Completion Date]@row), TODAY(), [Completion Date]@row - 1)), "No Submitted Date")
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives