Unit count for Duration
Sirius_200
✭✭✭
In the Duration column, instead of "d" for days, is there a way to show "wks" (for weeks) or "mons" (for months)?
Answers
-
Hi @Sirius_200
The Duration column can be filled out with the following formats:
- Weeks (2w)
- Whole working days (4d)
- Partial working days (3.5d)
- Hours (7h)
- Minutes (60m)
- Seconds (500s) and milliseconds (50000ms)
- A combination of hours, minutes, seconds, and milliseconds (4h 30m)
- Elapsed time (lead with an e) indicates elapsed time duration (e3d, e5h, e3.5d, etc.). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
Here's the article with more information: Project Sheet Columns: Start Date, End Date, Duration, % Complete and Predecessors
Cheers!
Genevieve
Need more information? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao!👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.5K Get Help
- 448 Global Discussions
- 145 Industry Talk
- 481 Announcements
- 5.1K Ideas & Feature Requests
- 85 Brandfolder
- 152 Just for fun
- 73 Community Job Board
- 492 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 304 Events
- 37 Webinars
- 7.3K Forum Archives