Unit count for Duration

Sirius_200
✭✭✭
In the Duration column, instead of "d" for days, is there a way to show "wks" (for weeks) or "mons" (for months)?
Answers
-
Hi @Sirius_200
The Duration column can be filled out with the following formats:
- Weeks (2w)
- Whole working days (4d)
- Partial working days (3.5d)
- Hours (7h)
- Minutes (60m)
- Seconds (500s) and milliseconds (50000ms)
- A combination of hours, minutes, seconds, and milliseconds (4h 30m)
- Elapsed time (lead with an e) indicates elapsed time duration (e3d, e5h, e3.5d, etc.). A task with a duration in elapsed time ignores non-working time. The task will start and end in the amount of time specified regardless of working day length and non-working days in the sheet.
Here's the article with more information: Project Sheet Columns: Start Date, End Date, Duration, % Complete and Predecessors
Cheers!
Genevieve
Need more information? 👀 | Help and Learning Center